2012-12-20 - 5540 - Service Request - Planned order and BOM issue #US #ProductionBreakFix #plannedorders
5540 - Planned Order and BOM Issue.
Summary Description
1. Components were not able to determine when Trying to Create a Sub Contracting PO.
2. Conversion of Planned order to Production Order was not possible.
Admin Info
Title
|
5540 Planned Order and BOM issue
|
Requested by
|
Doug Snyder
|
Issue Date
|
12-20-2012
|
Resolved by
|
Adithya
|
Resolved Date
|
12-20-2012
|
Status
|
Complete
|
Detailed Description
(Include Screen Shots if required )
1. When Trying to create a Subcontracting PO system gives an error '' not possible to determine any components''. Components were not determined even BOM is maintained for the Subcontracting Material.
2. Planned Order was not been converted to production order, Error : Routing does not exist.
Analysis and Recommendations
(Include Screen Shots if required)
1. It was observed that BOM was existing for Sub Contracting material, but it was not valid for those dates which components needs to be exploded in the Purchase Order.
It was recommended to maintain BOM for those validity dates.
2. It was observed that, routing was existing for the finished Product, but was not valid for the explosion date.
It was recommended to re Run MRP, by having Planning Mode as ''3'', Delete and recreate, which creates a planned order with new explosion dates in which BOM was Valid.
Resolution
Issue was resolved.